Nasdaq Outlines Dates for DR Site Migration

Exchange will hold a series of test days before the final cutover to the new site.

nasdaq-1

Nasdaq will go live with the new DR setup on the eighth floor of Equinix's CH4 datacenter at 350 East Cermak Road in Chicago on Aug. 15, and will run in parallel with the Ashburn site for five months before shutting down distribution of certain feeds from Ashburn on Jan. 29, 2016, followed by the migration of post-trade, back-office and reporting services in early 2016.

During the migration, Nasdaq will treat the Chicago location as a live Point of Presence for firms to receive market data and s